Bringing a steam engine back to working order is long, skilled work. This page shows where 80064’s restoration stands and what is still to do.
The restoration is well under way. The aim is to return 80064 to service on the West Somerset Railway in the summer of 2028, after a short running-in period on the East Somerset Railway.
Her boiler is being repaired by Riley and Son in Lancashire, while the chassis is being overhauled by the volunteer team at the East Somerset Railway’s workshops at Cranmore.
Progress at a glance
| Part of the engine | What it does | Status |
|---|---|---|
| Boiler | Makes the steam. It must pass an insurance inspection and pressure tests before the engine can run. | In progress at Riley and Son: a new front tube plate and a new front section of the boiler barrel are being made. |
| Smokebox | Houses the chimney and blastpipe, which draw the fire. | In progress: new liner plates and fittings riveted in, and new steam pipe glands made. |
| Frames | The steel backbone that everything else is fixed to. | In progress at Cranmore: cleaned, primed and now being painted. |
| Wheelsets and axleboxes | Carry the engine’s weight and turn the power into motion. | In progress: axle journals being skimmed and polished at Riley and Son, and new axlebox crowns being made. |
| Bogie and pony truck | The smaller wheels that guide the engine into curves. | In progress: bogie stripped and its wheels removed for cleaning. |
| Cylinders, rods and valve gear | Turn steam pressure into movement and control speed and direction. | In progress: coupling and connecting rod bearings removed, to be remetalled or renewed. |
| Side tanks and bunker | Carry the water and coal. | In progress: cleaned by water blasting. |
| Cab | Where the crew drive and fire the engine. | To confirm |
| Brakes, pipework and fittings | Stop the train safely and carry steam, water and air around the engine. | To confirm |
| Painting and lining | The final coat of British Railways lined black. | To confirm |
Filled in from the restoration posts up to 25 October 2026. Please check it, fill in the rows marked ‘To confirm’, and update the date under the table whenever you change it.
How a restoration works
- Assessment and dismantling. The engine is stripped down and every part is examined and recorded.
- Boiler work. Worn plates, tubes and stays are repaired or replaced. This is usually the largest single cost.
- Frames and wheels. Frames are checked and repaired; wheels are re-profiled and axleboxes rebuilt.
- Cylinders, motion and brakes. The moving parts are refurbished to fine tolerances.
- Reassembly. The engine is rebuilt, piece by piece.
- Testing. The boiler is tested under water and then steam pressure, followed by trial runs.
- Painting. Finally, the livery and lining go on, and the engine returns to service.
Latest updates
-

Welcome to the new 80064 website
Follow the restoration of 80064, read her story and find out how you can help.
-

80064 Restoration Update – Great Progress Despite the Wind
It was a challenging start to the day at Cranmore, with the windy weather causing frequent power cuts. For a while, it wasn’t clear quite…
-

80064 Axlebox Crowns Update
The Axlebox crown is the gunmetal bearing pressed into the top of the Axlebox which sits on the journals of the axles. This crown has…
Can you help with skills?
If you have engineering, machining, painting or project experience and would like to help, please get in touch.
Confirm whether volunteers are being sought for 80064, and who they should contact.
Help return 80064 to steam
The restoration is funded entirely by donations. If you are a UK taxpayer, Gift Aid adds 25p to every £1 you give, at no cost to you.